OWENS TRANSPORT - ASSOCIATED BUILDERS

Speedpro have commenced work on the post tensioned slabs at Owens Transport in Altona for Associated Builders. There will be 8,500m2 of slabs to complete with VSL completing the PT works. Slabs will be completed in 7 pours with an average of 450m3 of concrete per pour.